Retail DAO Sprint Backlog

   SpringboardThis topic is related to Springboard. |   Form Builder |  Retail DAO 4.0 This feature was updated in Retail DAO 4.0.

Sprint Backlog

Use this as a guide to the tasks required in the early sprints of a Standard Springboard implementation. This work can start once the prerequisites listed in the Client Task List have been met.

Sprint 0 – Setup default Springboard

Item Description

Spike

Review requirements received from client so far - agree that client has provided sufficient requirements in Customization Specification, Visual Specification, Product Specification, Email Specification documents.

Task

Total number of transactions that match the metric selected, such as Abandoned. This number is also expressed as a percentage for abandonments, field error rates and completion rate.

Task

Completion rate. This is expressed as a percentage of the total number of field commencements. Field commencements are recorded only if the field is touched by a user.

Task

The average number of times a field error occurs. Including validation and mandatory errors. This is expressed as a percentage of the total number of field commencements. Field commencements are recorded only if the field is touched by a user.

Spike

Team agrees on development/QA process and workflow

Spike Team agrees on development/QA/UAT process and workflow.

Task

Whitelist Integrations.

Task

Test automation project working and all tests pass.

Task

Team reviews project and agrees that solution is a “clone” of a Standard Springboard.

Sprint 1 – Begin configuration of Standard Springboard implementation

Item Description

Task

Update project to follow Customization Specification.

Task

Update project to follow Visual Specification.

Task

Update project to follow Product Specification.

Task Update project to follow Email Specification.

Task

Configure Integrations/Vendor Credentials.

Task

Configure Integrations/Vendor Credentials

Task

Team reviews project progress.

Task

Test automation project working and all tests pass.

Task

Bank Core Integration.

Sprint 2 – Continue configuration of Standard Springboard implementation

Item Description

Task

Continued work to follow Customization Specification.

Task

Continued work to follow Visual Specification.

Task

Continued work on Bank Core Integration.

Task

Test automation project working and all tests pass.

Task Team reviews project progress – goal of agreeing that Standard Springboard implementation is complete.

Task

Team reviews project progress – goal of agreeing that Base Springboard implementation is complete

Sprint 3 – Begin Custom Work.

 

Next, learn about Springboard client task list.